Drawdown 5-year plan

Drawdown Five-Year Plan for Highland Lake 2008-2014


Year Open Gate Close Gate Drawdown Water Level
(Gauge Indicator)
Water Level
2008-2009 November 1, 2008 January 15, 2009 Three Feet Lower to 8.9 Feet Raise to 11.9 Feet
2009-2010 October 15, 2009 January 15, 2010 Six to Eight Feet Lower to 5.9 to 3.9 Feet Raise to 11.9 Feet
2010-2011 October 15, 2010* December 1, 2010** Emergency
Five-Foot Drawdown
Lower to 8.9 Feet Raise to 11.9 Feet
2011-2012 November 1, 2011 January 15, 2012 Three Feet Lower to 8.9 Feet Raise to 11.9 Feet
2012-2013 November 1, 2012 January 15, 2013 Three Feet Lower to 8.9 Feet Raise to 11.9 Feet


Intent is to have six-foot to eight-foot drawdown in 2013-2014.

NOTE: Adjustments will be made to accommodate precipitation and to maintain as constant a water level as possible until "ice off" (usually around April 15). After "ice off," the gate will be closed to allow for a natural refill over the spillway level of 11.9 feet.

All footage is as measured on the gauge at the gatehouse.

*Adjustment: Emergency five-foot drawdown for cleanup of Resha Beach debris.

**Close gate, at the latest, on December 1, 2010 regardless of whether target depth has been reached and allow lake to refill naturally to three feet below spillway level.

Back to Home Page